Pauline and Alan's Case Study
Pauline
and Alan's case study is not one of those which went through without
a hitch. In fact, a project which should have taken 3 months to
complete took almost exactly a year.
Pauline and Alan have a 4 bedroomed detached house which would
be ample for most people! However, as Pauline was expecting her
4th baby and Alan was going to working from home, they needed an
extra bedroom and a study downstairs. They looked at moving house
but the actual house would cost at least another £50,000 and
then add on the moving costs it wasn't really feasible.
They looked into the possibility of extending to the side of their
property, where they currently had a wooden play house. They asked
for 2 architects to come around and give them advice and a quote.
They decided on one of them who proposed an extension that would
give an 8ft by 14ft room downstairs and a slightly smaller bedroom
upstairs. Access was not a problem as they already had a window
upstairs at the side. This could easily be converted into a doorway.
Plans were drawn up and planning permission given. Building regulations
also went through without any problems. They found a couple of builders
who had been recommended by friends and obtained quotes from both.
The quote was to include replacing the wooden windows in the main
part of the house with double glazed UPVC. The quotes arrived and
were similar - around £20,000. They found out that both builders
stated they were members of the Federation of Master Builders. However,
when they checked one was and the other was not. They decided to
use the one who was a member. They obtained a contract from the
FMB which they would ask the builder to sign. They also opted for
the guarantee that can be purchased which acts in a similar way
to the NHBC guarantee for the extension. It would cover them for
10 years.
Work started and they were given a rough finish date 3 months hence.
The builder started to dig the foundations. This in itself seemed
to take a long time - over 2 weeks. Then the problem occurred. The
foundations of the main house were deeper than standard. A small
hole 2 metres deep was dug and still the bottom of the main foundations
were not found. The council buildings inspector was called in for
advice. They suggested a special floating type of foundation which
is made of reinforced concrete. This would mean that a shallower
hole could be used, though extra cost would be incurred with the
metal work in the concrete. This was completed.
Then Pauline and Alan received the bill. An extra £8000 was
being asked by the builder. The figures given on the bill did not
match with what had happened. Extras skips were being charged for,
when he had dug a smaller hole than his original plan. Hours worked
did not seem to add up. Pauline and Alan commented on the figures
but the builder insisted that they were correct. After several weeks
of argument, quantity surveyors were brought in by both sides to
decide how much should be paid. By this stage the builder had walked
off site and left the couple with nothing but a concrete floor,
and a 3ft high brick wall. Finally, an amount was settled upon and
paid.
The problem was that Pauline and Alan now had to find a new builder
who would take on the project. This was difficult as most builders
in the area were very busy. Eventually, they found one who would
start in a month's time. He would be working on two projects at
once so there was no guarantee how long the project would take.
Work restarted, but some of the brick work had to be taken down
and rebuilt. The new chimney was also not the correct size and had
to be redone.
Work continued very slowly over the next few months. Before the
work had started, Pauline said as long as it's finished before the
baby comes everything will be alright. However, the new arrival
came and still the building work wasn't finished.
Almost a year to the day, the extension was finished. New windows
were put in the main house and decorating was completed. Alan moved
into his new office and their oldest daughter moved into the new
bedroom upstairs.
So, what was there overall impression of having an extension? Yes,
they are pleased with what they have now. A five bedroomed house
with a good sized study and a real fire with chimney, for a lot
less expense compared to moving. But, whether they would have another
extension. I think the answer is a definite NO.
|