House Extension Case Study - Janet & John
Janet
& John (no, not from the children's books!) currently live somewhere
in the East Midlands, in a 4 bedroomed detached house. They have
2 young children, John works full-time and Janet works part-time
from home. Her office is the corner of the dining room at present,
though she is quickly out growing this space. They ideally need
an extra room downstairs.
"We need to move to a bigger house" said John one day.
But when they looked at the price difference between their 4 bedroomed
house and a similar sized house with a study it frightened them.
An extra £40,000 would be needed to provide just this one
small room downstairs, and also the houses of this style were not
really in the area of town they wished to live.
How about Extending?
Janet suggested that they look into extending their house. They
had a good sized garden, though they wouldn't need to take up too
much space to accommodate a study. They would also gain from a larger
kitchen - the extension would be 30ft by 8ft when finished. Janet
contacted a local planner (an architectural technologist who had
been recommended by a friend) who came around to have a chat. He
made some good suggestions and came back a few days later with a
quote for £750 for preparing the initial
plans, submitting them to the council and then preparing and submitting
the building regulations plans. This quote did not include the actual
fees to the council which would add up to about £200.
Janet arranged for another quote but that came out at £2000,
so they went with the first quote.
Plans
The
plans were drawn up and once checked by Janet and John, were submitted
to the council. John was slightly concerned as there was two black
drains where the extension was going to built. They were told that
these could either be covered over with a special cover within the
floor of the extension, or they could be moved. This latter option
is the one they chose. Janet notified the neighbours of their plans
as they would probably get letters from the council. After a few
weeks a representative from the council came to look at the house
and check the the plans were correct and that the extension would
not affect any neighbours property. Planning Permission was given
after about 7 weeks. Building Regulations plans were automatically
submitted by the planner who would also send out requests for quotations
to local recommended builders.
Getting the Quote
Fortunately a very reputable firm of builders had a cancellation
at the time the Building Regulations were being submitted and they
therefore agreed to take on Janet & John's project. They provided
a quotation of £21,000 including VAT for
the building work. This would be payable in 3 parts - first when
DPC level was reached, second at plate level (before the roof is
put on) and the last payment when all the work was complete. This
was agreeable to Janet & John.
Building Work Starts
Work
would start within the next 2 weeks. So, on a Wednesday morning
in August at 8am builder arrived and immediately started work on
demolishing part of the garden wall. This would allow for easy access
for the mini digger and dumper trucks that would be needed for digging
the foundations. By Friday, 2pm the foundation trench was completed
and the first inspection by the council took place. Everything was
Ok so the concrete was poured in. This would be allowed to dry over
the weekend and the brickwork started on Monday. The new brickwork
was to be "cut-in" to the existing wall to make it look
less like an extension.
DPC (Damp Proof Course)
Enough
bricks and brieze blocks were built up to go up to the DPC height.
The plastic sheet was laid ready for the second inspection by the
council. After this has occurred, more concrete was laid to make
the base of the extension. It was now starting to look like a room.
The first payment of a £7000 was paid to the builders. Bricking
continued for the next week, until the roof height (plate level)
had been reached. Janet & John were amazed at the speed of the
building work, though there was 4 men working on the project all
the time.
Roof
Watching
the roof being added started to give the impression of a real building.
The speed again was amazing, the whole roof being completed within
3 days. Spaces had been left for 2 extractor units as the cloakroom
in the house was having it's window blocked up and also the size
of the kitchen now warranted an extra extractor fan due to new building
regulations on ventilation.
Windows and Doors
A window consultant came around and measured up for the doors and
windows. Two patio type doors were being used and discussions were
needed due to new regulations about the minimum size of door openings
to allow for disabled access. It was decided that 2 double-opening
french doors would be used. All these new windows and doors would
have ventilation strips at the top, again due to building regulations.
This regulation does not apply to replacement windows. There would
be a two week wait whilst the windows were manufactured.
Knock Through
Once the windows were installed the extension section was now secure
and the knock through of the kitchen wall could begin. An extra
£80 had already been paid to a quantity surveyor for him to
calculate the size of the RSJ beam that would be needed to replace
the wall that was to knocked through.
It took a day for all the knocking down of the wall and inserting
the RSJ to be complete, but when finished the size of the kitchen
now started to become apparent. It's completed size would be 19ft
by 11ft. There would now be major problems with using the kitchen
as the sink was on the wall which was no longer there. However,
the builders left the plumbing connected so that it could be used.
Emptying the sink was interesting - it had to emptied down the cloakroom
toilet - the outlet from the sink in there had been lost as soon
as building work had started!
Plaster and Floor
The
electrician came and positioned the new sockets for both rooms.
He would need to return once the plastering was complete. It was
now time for the plasterers to come in and do their job. The new
ceilings in the kitchen and study were to be artexed to match the
rest of the house. However, the artexer (sub-contractor) did not
do a good job, so the builder arranged for the plasterer to come
and re-do the ceiling, this time with plaster. Most ceilings these
days are plastered rather than using artex. The floors to the kitchen
and study were done, the one in the kitchen after the plumbing for
the sink (which was moving into the extended part, was complete.
Janet did not notice any disruption to the water supply even though
the main cock-stop was moved, the old position would be right in
the middle of the new kitchen floor.
Once all the new plaster was dry, it was time to start installing
the new kitchen. The builders did this, though Janet and John had
already assembled all the units. The kitchen was starting to look
like a kitchen again, units going in, appliances being put in their
new positions.
Finishing Touches
Once
the plaster was completely dry - this took a few days, it changes
colour as it dries - decorating could begin. Janet was advised that
the first coat should be diluted 50% with water as the plaster tends
to soak in what is put on top. Another two coats later and the study
was finished. Next the kitchen. This was more difficult as Janet
had to around the cupboards and also do the ceiling over the top
of the cupboards. The use of a radiator roller was useful here.
Tiling was done and then finally the flooring came in.
Overall Costs
The list of the costs involved with the extension for Janet &
John was as follows:
| Item |
Cost |
| Architects Planning Fee |
£400 |
| Council Planning Permission Fee |
£110 |
| Architects Building Regulations Fee |
£350 |
| Council Building Regulations Fee |
£125 |
| Council Inspection Fee |
£260 |
| RSJ Calculations |
£80 |
| Builders Cost |
£21000 |
| Patio and Extra Costs Paid to Builder |
£2000 |
| Kitchen + Flooring |
£4300 |
| Total Cost |
£28625 |
Overall Opinion
Janet & John's requirement was to have a study. With the extension
this objective was met and they also gained a larger kitchen. The
overall cost came to just over £28,000 including the cost
of the kitchen and flooring. This was good value for money compared
to the minimum £50,000 that they would need to have found
to move house to a property worth at least £40,000 more than
their current property.
It was a good experience and overall took about 2 months to complete,
including fitting a brand new kitchen.
|